Participation in the Pathway Program through Development of the Platform and Cabling Solution

February 2020 – September 2021

The Pathway Program - Cable & Platform Development / Sensor Integration

The Pathway Program: Validating reliable environmental monitoring for ocean energy projects

April 2019 – October 2021

OERA created The Pathway Program to solve a critical problem impeding the in-stream tidal energy industry: a lack of reliable and validated technologies and methods to monitor and report fish-turbine interactions in high-flow, highly turbulent environments, leading to regulatory uncertainty and i

Review of Nova Scotia Power Transmission System Interconnection Requirements

April – May 2021

Power Advisory was engaged by OERA on behalf of the Nova Scotia Department of Energy & Mines to review the recently released Nova Scotia Power Transmission System Interconnection Requirements (TSIR) and identify any gaps between recommendations made by Power Advisory in their August 2020 repo

Environmental Monitoring System Development

November 2019 – April 2021

The Pathway Program - Technology Validation: Echosouders & Passive Acoustic Monitoring Device

Acceleration/Particle Velocity (PA/PV) Measurement System Evaluation in a Tidal Environment

February 2017 – December 2018

The objective of this project was designing and running a field experiment to test the performance of the Particle Acceleration/Particle Velocity (PA/PV) vector sensor.

Feasibility Study: Tidal Sector Service Barge/Drydock

April – November 2018

The study investigates the feasibility of developing a generic, shared-use, multi-function turbine transport deployment and retrieval barge/drydock for use by the Nova Scotia tidal energy sector.

Analysis of Tidal Turbine Mooring Systems in Turbulent Flows Applying the (Wind Industry) FAST Simulation Tool and DSA ProteusDS Software

March – September 2018

For floating tidal turbine platforms, the turbine forces and resulting platform motions have a direct impact on the lifetime of its moorings and cables. This means the tidal sector must predict accurate tidal turbine loading on floating platforms to determine mooring life and cable longevity.

Assessing Corrosion, Wear, Fatigue and VIV on Moorings and Cabling to Reduce Risk in Marine Operations

October 2017 – August 2018

The cost of cabling and moorings over the entire life of a tidal energy project is a significant proportion of total project expenditures and the potential failure of these components remains a major risk for the emerging tidal energy sector.

Using Dry Ports to Support Nova Scotia’s Tidal Industry

March – June 2018

This study investigates two Nova Scotia “dry ports” and their potential in supporting the Bay of Fundy region’s emergent tidal energy industry. The term ‘dry port’ refers to a port where the harbour bottom is mainly exposed at low tide.